Construction
Upcoming Construction Plans
- Complete work inside the West Holding Tank and install Flexible Membrane Digester Gas Cover
- Complete upgrades in the East Digester
- Repair East Holding Tank upper walls and construct new aluminum dome cover
- Refurbish DAF 1 and 2 into the new sidestream treatment system
- Complete High Mast Lights
Work Completed
February 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Procured additional BAS controls this month.
- Began the electrical work on associated with the East Digester.
- Continued work on the new Water Main into the Blue River WWTP.
- Continued installing piping and ductwork at various areas of the Biosolids Building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
- Completed additional work associated with the existing elevator control room at the Admin Building basement.
- Began the electrical rough-in and cable pulling at the Cake Loadout structure.
- Installed the exhaust fan at the Cake Loadout structure.
- Completed installing the Cake Loadout PEMB wall and roof panels.
- Continued installing cable tray and wire pulling at the Utility Corridor.
- Installed the blowers and piping at the West Holding Tank.
- Installed the blowers and piping at the upper floor of the Sidestream Building.
- Continued the electrical work inside the Sidestream Electrical Building.
- Continued duct installation at the Odor Control area.
- Continued installing the duct bank to DAF 3.
January 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Procured additional BAS controls and aluminum ductwork this month.
- Began work on the new Water Main into the Blue River WWTP.
- Continued installing piping and ductwork at various areas of the Biosolids Building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
- Continued installing the Cake Loadout PEMB wall and ceiling panels.
- Continued installing cable tray and wire pulling at the Utility Corridor.
- Continued installing the cable catch system at the West Holding Tank,.
- Installed additional above ground piping at the Waste Gas Flare.
- Installed stucco at the WHT walls.
- Continued the electrical work inside the Sidestream Electrical Building.
- Formed and poured equipment pads at the Sidestream Treatment Building.
- Continued duct installation at the Odor Control area.
- Continued installing the duct bank to DAF 3.
→ Click here to view construction work completed in 2021 and 2022.
→ Click here to view construction work completed in 2023.
→ Click here to view construction work completed in 2024.