Construction
Upcoming Construction Plans
- Complete upgrades in the West Digester
- Startup Pre-THP Feed Pumps and Centrifuges, Pre-THP Silos and THP Feed Pumps
- Commission the new THP System
- Repair East Holding Tank upper walls and construct new aluminum dome cover
- Refurbish DAF 1 and 2 into the new sidestream treatment system
- Complete High Mast Lights
Work Completed
July 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Procured additional materials for the fire alarm system.
- Completed some additional change order work associated with the West Digester and HVAC systems.
- Completed several activities associated with the Holding Tank Room.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building, Cake Loadout, Waste Gas Flare and Holding Tank area.
- Continued Installation and functional testing for several systems at the Biosolids Building and THP area.
- Continued installing Sidestream Reactor 1 equipment.
- Begin installing the 36” diameter FRP duct at West Holding Tank.
- Completed the piping work inside the EQ Basin.
- Completed parking lot striping, installed parking blocks and completed more concrete sidewalks.
June 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Procured addition materials for the aluminum duct, high pressure wash system, fire alarm and BAS controls.
- Completed some additional change order work associated with the West Digester and the front entrance security gate.
- Completed several activities associated with placing the West Holding Tank in service.
- Completed some remaining piping and insulation work at the Biosolids building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
- Continued Installation and functional testing for several systems at the Biosolids Building.
- Continued electrical rough-in, cable pulling and wiring terminations at the Cake Loadout structure, THP, Odor Control areas, existing Boiler Room, Transfer area, Sidestream area and new Flare.
- Continued Installation Testing at the THP area.
- Completed getting the truck scales and monorail crane operational.
- Installed the pressure wash system at Cake Loadout.
- Continued electrical work at the West Holding Tank Transfer Room and Digester Building.
- Continued installing Sidestream Reactor 1 equipment.
May 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Completed some additional change order work associated with the East Digester, Area 70 Transfer Room HVAC upgrades, replacing Digester Mixing pump VFDs and water main installation into the plant.
- Installed a few additional FRP doors at the Biosolids Building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
- Continued Installation Testing for several systems at the Biosolids Building.
- Continued electrical rough-in, cable pulling and wiring terminations at the Cake Loadout structure.
- THP, Odor Control areas and the existing Boiler Room and Transfer area.
- Began Installation Testing at the THP and Odor Control areas.
- Continued installation of the Cake Loadout mezzanine and stairs.
- Continued electrical work at the West Holding Tank Transfer Room and Digester Building.
- Continued additional modifications to the existing EQ Basin.
- Continued duct installation at the Transfer area.
- Continued placing additional concrete paving, curbs and sidewalks and began backfilling some curbs and fine grading a few areas.
April 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Completed some additional change order work associated with the East Digester, Birmingham Farm Pumps, Area 79 Transfer Room HVAC upgrades, water main installation into the plant and installed a 12” SS valve on the West Digester gas line.
- Continued work on the new Water Main into the Blue River WWTP.
- Continued installing some piping, ductwork and insulation at various areas of the Biosolids Building.
- Installed some additional FRP doors at the Biosolids Building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building
- Continued electrical rough-in, cable pulling and wiring terminations at the Cake Loadout structure, THP, Odor Control areas and the existing Boiler Room and Transfer area.
- Completed all work associated with placing the East Digester back in service.
- Continued additional modifications to the existing EQ Basin.
- Continued duct installation at the Transfer area.
- Began installing the West Holding Tank gas membrane system.
- Installed additional storm drain piping.
- Continued placing additional concrete paving, curbs and sidewalks
- Installed additional storm drain piping and curb inlets.
March 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Continued electrical work associated with the East Digester.
- Continued work on the new Water Main into the Blue River WWTP.
- Continued installing piping and ductwork at various areas of the Biosolids Building.
- Installed some additional FRP doors at the Biosolids Building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
- Continued electrical rough-in, cable pulling and wiring terminations at the Cake Loadout structure, THP, West Holding Tank Blower pad and Odor Control areas.
- Installed the overhead doors at the Cake Loadout Building.
- Continued installing cable tray and wire pulling at the Utility Corridor.
- Continued piping installation at the upper floor of the Sidestream Building.
- Continued the electrical work inside the Sidestream Electrical Building.
- Installed the chemical feed panels at the Sidestream Building.
- Placed concrete fill at the Sidestream Reactor No. 1.
- Began additional modifications to the existing EQ Basin.
- Began duct installation at the Transfer area.
- Installed additional storm drain piping.
February 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Procured additional BAS controls this month.
- Began the electrical work on associated with the East Digester.
- Continued work on the new Water Main into the Blue River WWTP.
- Continued installing piping and ductwork at various areas of the Biosolids Building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
- Completed additional work associated with the existing elevator control room at the Admin Building basement.
- Began the electrical rough-in and cable pulling at the Cake Loadout structure.
- Installed the exhaust fan at the Cake Loadout structure.
- Completed installing the Cake Loadout PEMB wall and roof panels.
- Continued installing cable tray and wire pulling at the Utility Corridor.
- Installed the blowers and piping at the West Holding Tank.
- Installed the blowers and piping at the upper floor of the Sidestream Building.
- Continued the electrical work inside the Sidestream Electrical Building.
- Continued duct installation at the Odor Control area.
- Continued installing the duct bank to DAF 3.
January 2025
- Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
- Procured additional BAS controls and aluminum ductwork this month.
- Began work on the new Water Main into the Blue River WWTP.
- Continued installing piping and ductwork at various areas of the Biosolids Building.
- Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
- Continued installing the Cake Loadout PEMB wall and ceiling panels.
- Continued installing cable tray and wire pulling at the Utility Corridor.
- Continued installing the cable catch system at the West Holding Tank,.
- Installed additional above ground piping at the Waste Gas Flare.
- Installed stucco at the WHT walls.
- Continued the electrical work inside the Sidestream Electrical Building.
- Formed and poured equipment pads at the Sidestream Treatment Building.
- Continued duct installation at the Odor Control area.
- Continued installing the duct bank to DAF 3.
→ Click here to view construction work completed in 2021 and 2022.
→ Click here to view construction work completed in 2023.
→ Click here to view construction work completed in 2024.