Construction

Project timeline

Upcoming Construction Plans

  • Complete work inside the West Holding Tank and install Flexible Membrane Digester Gas Cover
  • Complete upgrades in the East Digester
  • Repair East Holding Tank upper walls and construct new aluminum dome cover
  • Refurbish DAF 1 and 2 into the new sidestream treatment system
  • Complete High Mast Lights

Work Completed

February 2025

  • Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
  • Procured additional BAS controls this month.
  • Began the electrical work on associated with the East Digester.
  • Continued work on the new Water Main into the Blue River WWTP.
  • Continued installing piping and ductwork at various areas of the Biosolids Building.
  • Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
  • Completed additional work associated with the existing elevator control room at the Admin Building basement.
  • Began the electrical rough-in and cable pulling at the Cake Loadout structure.
  • Installed the exhaust fan at the Cake Loadout structure.
  • Completed installing the Cake Loadout PEMB wall and roof panels.
  • Continued installing cable tray and wire pulling at the Utility Corridor.
  • Installed the blowers and piping at the West Holding Tank.
  • Installed the blowers and piping at the upper floor of the Sidestream Building.
  • Continued the electrical work inside the Sidestream Electrical Building.
  • Continued duct installation at the Odor Control area.
  • Continued installing the duct bank to DAF 3.

January 2025

  • Goodwin and various subs and suppliers are continuing to develop and submit O&Ms and Training Plans, and a few other submittals for review.
  • Procured additional BAS controls and aluminum ductwork this month.
  • Began work on the new Water Main into the Blue River WWTP.
  • Continued installing piping and ductwork at various areas of the Biosolids Building.
  • Continued electrical wire pulling and terminations at several areas of the Biosolids Building.
  • Continued installing the Cake Loadout PEMB wall and ceiling panels.
  • Continued installing cable tray and wire pulling at the Utility Corridor.
  • Continued installing the cable catch system at the West Holding Tank,.
  • Installed additional above ground piping at the Waste Gas Flare.
  • Installed stucco at the WHT walls.
  • Continued the electrical work inside the Sidestream Electrical Building.
  • Formed and poured equipment pads at the Sidestream Treatment Building.
  • Continued duct installation at the Odor Control area.
  • Continued installing the duct bank to DAF 3.

    Click here to view construction work completed in 2021 and 2022.

    → Click here to view construction work completed in 2023.

    → Click here to view construction work completed in 2024.

      Blue River Biosolids Facility 2024 Year in Review

      Construction is moving right along at KC Water’s Blue River Wastewater Treatment Plant! The site...

      Blue River Biosolids Facility 2023 Year in Review

      Check out the construction progress at KC Water’s Blue River Wastewater Treatment Plant (WWTP)....

      Micro Aeration = Renewable Energy

      What does it all mean? Anaerobic means “without oxygen”. Micro aeration is adding a small amount...